Retainage in Florida: What the B&F Exam Expects You to Know

Updated October 2026

Retainage is the part of each progress payment the owner holds back until the job is finished. It protects the owner against incomplete or defective work and unpaid subcontractors. For the contractor it is money earned but not yet collected, which is why it matters for cash flow. The Business and Finance exam tests retainage two ways: the Florida statutes that limit it, and the pay-application math.

This page summarizes what the statutes say for exam study. Retainage statutes have been amended several times, so check the current statute before relying on a percentage for a real contract.

Public projects: the 5% cap

Florida caps retainage on most public construction contracts at 5% of each progress payment.

Both statutes also say:

No 50% step-down in the current statute

Some study materials describe a rule of 10% retainage until the job is 50% complete, then 5% after that. That is not what the current text of F.S. 255.078 or 218.735 says. Both set a flat maximum of 5% of each progress payment. A contract may still use a lower or declining schedule. If you see the 10%/50% rule in a practice question, check which version of the law it is based on.

Closeout on public jobs

After substantial completion, the contract must provide for a punch list with the estimated cost to complete each item. On projects under $10 million, the list is developed within 30 days of substantial completion. Within 20 business days after the list is developed, the entity pays the remaining contract balance, including retainage, less 150% of the estimated cost of the open items (F.S. 255.077 and 218.735(7)).

Private projects: no statutory percentage cap

For private work, Florida does not set a maximum retainage percentage. The rate is whatever the contract says. F.S. 715.12, the Construction Contract Prompt Payment Law, controls timing:

A separate statute, F.S. 713.346, requires anyone who receives payment on a construction contract to pay undisputed obligations to the people who supplied labor, services or materials, and gives them remedies if those amounts go unpaid for more than 30 days. It is a payment rule, not a retainage cap.

Summary table

Public, state entity Public, local government Private
Statute F.S. 255.078 F.S. 218.735(8) F.S. 715.12(7)
Maximum retainage 5% of each progress payment 5% of each progress payment Set by contract
Contracts excluded from the cap $200,000 or less; conflicting federal funds $200,000 or less; conflicting federal funds Not applicable
Final release Balance less 150% of punch-list costs within 20 business days of the list Same Within 14 days of substantial completion events and punch list

Worked example 1: public pay application

A county hires a contractor for a $2,400,000 building (not federally funded). The contract withholds the maximum retainage the statute allows. Through Pay Application 4, completed work totals $1,080,000. Previous payments total $760,000.

Step 1. Retainage rate. Local government, contract over $200,000: 5% maximum.

Step 2. Retainage on work to date. $1,080,000 × 5% = $54,000

Step 3. Earned less retainage. $1,080,000 − $54,000 = $1,026,000

Step 4. Less previous payments. $1,026,000 − $760,000 = $266,000

The current payment due is $266,000, and the county is holding $54,000 in retainage.

Worked example 2: private job with a contract step-down

A private owner's contract for $900,000 says 10% retainage on work until the job is 50% complete, then 5% on work after that, with the earlier retainage staying in place. The job is now 80% complete.

Step 1. Work billed to date. 80% × $900,000 = $720,000

Step 2. Split the work at the 50% point. First half: 50% × $900,000 = $450,000 Remaining work billed: $720,000 − $450,000 = $270,000

Step 3. Retainage on each part. $450,000 × 10% = $45,000 $270,000 × 5% = $13,500

Step 4. Total retainage held. $45,000 + $13,500 = $58,500

This step-down is legal here because it is a private contract term. On a public job over $200,000, the 10% portion would exceed the 5% statutory cap.

How retainage appears on the books

Key numbers to tab in your book

Practice pay applications

Retainage questions combine a rule with arithmetic, and the arithmetic is where points are lost. Our Florida Business and Finance Exam Prep includes original pay-application and retainage questions with each step worked out, plus 90 days of practice across the full exam. Related guides: construction lien law and percentage of completion.

Practice questions

Practice question 1

A Florida county construction contract worth $3 million (not federally funded) is subject to s. 218.735, F.S. The contractor's current progress payment request is for $80,000 of earned work. What is the MAXIMUM retainage the county may withhold from this payment, and what is the minimum net payment?

  1. A$8,000 retainage; $72,000 net
  2. B$2,000 retainage; $78,000 net
  3. C$4,000 retainage; $76,000 net
  4. D$0 retainage; $80,000 net
Show answer

Answer: C. Under s. 218.735(8)(a), a local government may withhold no more than 5% of each progress payment: $80,000 x 5% = $4,000, leaving $76,000. The old 10%-until-50%-complete rule was replaced by the 5% cap (2023 amendments). Check the current statute.

Source: F.S. 218.735(8)(a)

Practice question 2

On a Florida public contract, a local government withholds retainage of 5% under F.S. 218.735(8). A progress payment request is for $64,000 of work. The amount withheld as retainage is at most:

  1. A$3,200
  2. B$6,400
  3. C$640
  4. D$4,800
Show answer

Answer: A. The statute limits retainage to no more than 5% of each progress payment: $64,000 x 0.05 = $3,200. $6,400 reflects the 10% rate used on many private contracts and under older public-contract rules.

Source: F.S. 218.735(8)(a)

Practice question 3

Pay application: work completed to date $180,000, retainage 10%, previous payments $112,500. What is the current payment due?

  1. A$67,500
  2. B$162,000
  3. C$31,500
  4. D$49,500
Show answer

Answer: D. Earned less retainage = $180,000 − $18,000 = $162,000; less previous payments $112,500 = $49,500. $67,500 forgets to deduct retainage.

Source: Standard accounting principles

Practice question 4

On a private $400,000 contract with 10% retainage withheld from each progress payment, the work is 60% complete. The contractor has already received $150,000. What is the current payment due?

  1. A$66,000
  2. B$90,000
  3. C$216,000
  4. D$75,000
Show answer

Answer: A. Earned to date = 60% x $400,000 = $240,000. Retainage = 10% x $240,000 = $24,000. Less previous payments: $240,000 - $24,000 - $150,000 = $66,000. $90,000 forgets retainage, and $216,000 forgets the previous payments.

Source: Standard progress billing arithmetic; F.S. 715.12(7) permits private retainage by agreement

Practice question 5

A $750,000 contract has 10% retainage until 50% complete and 5% retainage on work after that (retainage already held stays). At 70% complete, total retainage held is:

  1. A$52,500
  2. B$45,000
  3. C$37,500
  4. D$26,250
Show answer

Answer: B. First 50% = $375,000 x 10% = $37,500; next 20% = $150,000 x 5% = $7,500; total $45,000. $52,500 applies 10% to all $525,000 of completed work.

Source: Standard accounting/construction-management principle

These are from our bank of 466 original questions. Get the full Florida Business & Finance prep.