Retainage is the part of each progress payment the owner holds back until the job is finished. It protects the owner against incomplete or defective work and unpaid subcontractors. For the contractor it is money earned but not yet collected, which is why it matters for cash flow. The Business and Finance exam tests retainage two ways: the Florida statutes that limit it, and the pay-application math.
This page summarizes what the statutes say for exam study. Retainage statutes have been amended several times, so check the current statute before relying on a percentage for a real contract.
Public projects: the 5% cap
Florida caps retainage on most public construction contracts at 5% of each progress payment.
- State-level public entities: F.S. 255.078(1) says a public entity "may withhold from each progress payment made to the contractor an amount not exceeding 5 percent of the payment as retainage."
- Local governments (counties, cities and similar): F.S. 218.735(8)(a), part of the Local Government Prompt Payment Act, uses the same 5% limit.
Both statutes also say:
- The entity may withhold less than 5%, reduce the rate on a schedule in the contract, or release retainage early.
- If the entity releases retainage that belongs to subcontractors' or suppliers' work, the contractor must pass it on to them promptly.
- The cap does not apply to contracts with a total cost of $200,000 or less.
- The cap does not apply where federal funds are involved and federal requirements conflict with the prompt payment act.
- Amounts in a good-faith written dispute do not have to be released.
No 50% step-down in the current statute
Some study materials describe a rule of 10% retainage until the job is 50% complete, then 5% after that. That is not what the current text of F.S. 255.078 or 218.735 says. Both set a flat maximum of 5% of each progress payment. A contract may still use a lower or declining schedule. If you see the 10%/50% rule in a practice question, check which version of the law it is based on.
Closeout on public jobs
After substantial completion, the contract must provide for a punch list with the estimated cost to complete each item. On projects under $10 million, the list is developed within 30 days of substantial completion. Within 20 business days after the list is developed, the entity pays the remaining contract balance, including retainage, less 150% of the estimated cost of the open items (F.S. 255.077 and 218.735(7)).
Private projects: no statutory percentage cap
For private work, Florida does not set a maximum retainage percentage. The rate is whatever the contract says. F.S. 715.12, the Construction Contract Prompt Payment Law, controls timing:
- An owner and contractor may agree to withhold a portion of each progress payment until substantial completion (715.12(7)(a)).
- The owner must pay the balance, including retainage, within 14 days after substantial completion is certified, a certificate of occupancy is issued, or the owner takes possession, and the contractor completes the punch list.
- Late retainage accrues interest at the statutory rate.
- Contractors and subcontractors may also agree to retainage down the chain (715.12(7)(b)).
A separate statute, F.S. 713.346, requires anyone who receives payment on a construction contract to pay undisputed obligations to the people who supplied labor, services or materials, and gives them remedies if those amounts go unpaid for more than 30 days. It is a payment rule, not a retainage cap.
Summary table
| Public, state entity | Public, local government | Private | |
|---|---|---|---|
| Statute | F.S. 255.078 | F.S. 218.735(8) | F.S. 715.12(7) |
| Maximum retainage | 5% of each progress payment | 5% of each progress payment | Set by contract |
| Contracts excluded from the cap | $200,000 or less; conflicting federal funds | $200,000 or less; conflicting federal funds | Not applicable |
| Final release | Balance less 150% of punch-list costs within 20 business days of the list | Same | Within 14 days of substantial completion events and punch list |
Worked example 1: public pay application
A county hires a contractor for a $2,400,000 building (not federally funded). The contract withholds the maximum retainage the statute allows. Through Pay Application 4, completed work totals $1,080,000. Previous payments total $760,000.
Step 1. Retainage rate. Local government, contract over $200,000: 5% maximum.
Step 2. Retainage on work to date. $1,080,000 × 5% = $54,000
Step 3. Earned less retainage. $1,080,000 − $54,000 = $1,026,000
Step 4. Less previous payments. $1,026,000 − $760,000 = $266,000
The current payment due is $266,000, and the county is holding $54,000 in retainage.
Worked example 2: private job with a contract step-down
A private owner's contract for $900,000 says 10% retainage on work until the job is 50% complete, then 5% on work after that, with the earlier retainage staying in place. The job is now 80% complete.
Step 1. Work billed to date. 80% × $900,000 = $720,000
Step 2. Split the work at the 50% point. First half: 50% × $900,000 = $450,000 Remaining work billed: $720,000 − $450,000 = $270,000
Step 3. Retainage on each part. $450,000 × 10% = $45,000 $270,000 × 5% = $13,500
Step 4. Total retainage held. $45,000 + $13,500 = $58,500
This step-down is legal here because it is a private contract term. On a public job over $200,000, the 10% portion would exceed the 5% statutory cap.
How retainage appears on the books
- The contractor records retainage the owner withholds as retainage receivable, an asset.
- Retainage the contractor withholds from its subcontractors is retainage payable, a liability.
- Large retainage balances are a common cause of tight cash flow even on profitable jobs.
Key numbers to tab in your book
- Public construction retainage cap (5%)
- $200,000 contract threshold for the retainage cap
- Federal funds exception
- Punch list and the 150% holdback at closeout
- Private retainage and the 14-day payment rule
- Retainage receivable and retainage payable
Practice pay applications
Retainage questions combine a rule with arithmetic, and the arithmetic is where points are lost. Our Florida Business and Finance Exam Prep includes original pay-application and retainage questions with each step worked out, plus 90 days of practice across the full exam. Related guides: construction lien law and percentage of completion.
Practice questions
A Florida county construction contract worth $3 million (not federally funded) is subject to s. 218.735, F.S. The contractor's current progress payment request is for $80,000 of earned work. What is the MAXIMUM retainage the county may withhold from this payment, and what is the minimum net payment?
- A$8,000 retainage; $72,000 net
- B$2,000 retainage; $78,000 net
- C$4,000 retainage; $76,000 net
- D$0 retainage; $80,000 net
Show answer
Answer: C. Under s. 218.735(8)(a), a local government may withhold no more than 5% of each progress payment: $80,000 x 5% = $4,000, leaving $76,000. The old 10%-until-50%-complete rule was replaced by the 5% cap (2023 amendments). Check the current statute.
Source: F.S. 218.735(8)(a)
On a Florida public contract, a local government withholds retainage of 5% under F.S. 218.735(8). A progress payment request is for $64,000 of work. The amount withheld as retainage is at most:
- A$3,200
- B$6,400
- C$640
- D$4,800
Show answer
Answer: A. The statute limits retainage to no more than 5% of each progress payment: $64,000 x 0.05 = $3,200. $6,400 reflects the 10% rate used on many private contracts and under older public-contract rules.
Source: F.S. 218.735(8)(a)
Pay application: work completed to date $180,000, retainage 10%, previous payments $112,500. What is the current payment due?
- A$67,500
- B$162,000
- C$31,500
- D$49,500
Show answer
Answer: D. Earned less retainage = $180,000 − $18,000 = $162,000; less previous payments $112,500 = $49,500. $67,500 forgets to deduct retainage.
Source: Standard accounting principles
On a private $400,000 contract with 10% retainage withheld from each progress payment, the work is 60% complete. The contractor has already received $150,000. What is the current payment due?
- A$66,000
- B$90,000
- C$216,000
- D$75,000
Show answer
Answer: A. Earned to date = 60% x $400,000 = $240,000. Retainage = 10% x $240,000 = $24,000. Less previous payments: $240,000 - $24,000 - $150,000 = $66,000. $90,000 forgets retainage, and $216,000 forgets the previous payments.
Source: Standard progress billing arithmetic; F.S. 715.12(7) permits private retainage by agreement
A $750,000 contract has 10% retainage until 50% complete and 5% retainage on work after that (retainage already held stays). At 70% complete, total retainage held is:
- A$52,500
- B$45,000
- C$37,500
- D$26,250
Show answer
Answer: B. First 50% = $375,000 x 10% = $37,500; next 20% = $150,000 x 5% = $7,500; total $45,000. $52,500 applies 10% to all $525,000 of completed work.
Source: Standard accounting/construction-management principle
These are from our bank of 466 original questions. Get the full Florida Business & Finance prep.