Job Costing and Estimating: Overhead, Markup, Margin and Break-Even

Updated October 2026

Pricing a job correctly is where a contracting business makes or loses money, and it is where the Business and Finance exam puts a lot of arithmetic. The content outline lists "Determine Business Overhead" and "Preparing Bids/Proposals" in Area B (26% of the exam) and "Track Job Costs" in Area D (32%). This page works through the four ideas behind most of those questions: direct vs. indirect cost, overhead allocation, markup vs. margin, and break-even.

Direct costs vs. overhead

Direct (job) costs Indirect costs (overhead)
Materials installed on the job Office rent and utilities
Field labor and its burden (payroll taxes, workers' comp, benefits) Office salaries
Subcontracts Advertising, dues, phones
Equipment used on the job Accounting and legal fees
Job-specific permits and general conditions (superintendent, temporary facilities) Insurance and interest not charged to jobs

General conditions (the superintendent, job trailer, temporary power and similar items for one project) are a job cost even though they are not "bricks and sticks." They are usually figured by time: weekly cost × weeks on the schedule.

Labor burden turns a wage into a real cost. If a carpenter earns $25.00 per hour and burden is 32% of wages, the cost is $25.00 × 1.32 = $33.00 per hour. See payroll tax and workers' compensation for the pieces of burden.

Allocating overhead

Overhead has to be recovered from jobs. The usual approach is a predetermined rate based on a budget.

Overhead rate = budgeted annual overhead ÷ budgeted allocation base

Example: overhead as a percentage of direct cost

A contractor budgets $360,000 of overhead and $3,000,000 of direct job costs for the year.

Rate = $360,000 ÷ $3,000,000 = 12% of direct cost

Example: overhead on direct labor

Same overhead, but the base is $900,000 of budgeted direct labor. Rate = $360,000 ÷ $900,000 = 40% of direct labor. A job with $45,000 of direct labor is charged $45,000 × 40% = $18,000 of overhead.

The exam will tell you which base to use. Read carefully.

Building a bid price

Worked example

Estimated direct costs for a job are $400,000. The contractor applies overhead at 12% of direct cost, then profit at 10% of cost plus overhead.

Step 1. Overhead. $400,000 × 12% = $48,000 Step 2. Total cost. $400,000 + $48,000 = $448,000 Step 3. Profit. $448,000 × 10% = $44,800 Step 4. Bid price. $448,000 + $44,800 = $492,800

Shortcut: $400,000 × 1.12 × 1.10 = $492,800.

The trap is adding the percentages first: $400,000 × 1.22 = $488,000. That is wrong because profit is figured on cost plus overhead, not on direct cost alone.

Markup vs. margin

This is the most tested pricing concept on the exam, and the definitions are not interchangeable.

Formula
Price from markup Cost × (1 + markup)
Price from margin Cost ÷ (1 − margin)
Margin from markup Markup ÷ (1 + markup)
Markup from margin Margin ÷ (1 − margin)

Worked example

A job costs $80,000.

A contractor who wants a 20% margin but marks up 20% leaves $4,000 on the table on this job.

Conversion table

Markup on cost Equivalent margin on price
10% 9.1%
15% 13.0%
20% 16.7%
25% 20.0%
33.3% 25.0%
50% 33.3%
100% 50.0%

Margin is always smaller than the matching markup.

Break-even analysis

Break-even is the revenue (or volume) where gross profit exactly covers fixed overhead, so net profit is zero.

Break-even revenue = fixed overhead ÷ gross margin (or contribution margin) ratio

Example: revenue

Fixed overhead is $360,000 a year. Jobs average an 18% gross margin after direct costs.

Break-even = $360,000 ÷ 0.18 = $2,000,000 of revenue.

Check: 18% × $2,000,000 = $360,000 of gross profit, which covers overhead exactly.

Example: target profit

To earn $90,000 of pre-tax profit on top of break-even:

Required revenue = ($360,000 + $90,000) ÷ 0.18 = $2,500,000

Example: units

A contractor installs water heaters at $1,400 each with variable cost of $1,050 each. Fixed costs assigned to this line are $42,000 per year.

Contribution per unit = $1,400 − $1,050 = $350. Break-even = $42,000 ÷ $350 = 120 units.

Wrong answers divide by the price or by the variable cost instead of the contribution per unit.

Tracking job costs

Once the job starts, the estimate becomes the budget. Comparing actual to estimate by cost code tells you where money is being lost while there is still time to act.

Cost overrun % = (actual − estimate) ÷ estimate

A job estimated at $82,000 that comes in at $88,560 overran by $6,560 ÷ $82,000 = 8%.

Job cost reports also feed percentage of completion revenue recognition, so poor job costing produces poor financial statements.

Quick review

Concept Remember
Overhead rate Budgeted overhead ÷ budgeted base
Profit on cost plus overhead Multiply in sequence, do not add percentages
Markup Profit ÷ cost
Margin Profit ÷ price
Break-even Fixed costs ÷ margin ratio

Practice pricing math

Our Florida Business and Finance Exam Prep includes original overhead, markup, margin and break-even questions, each with worked steps, and 90 days of practice across the full exam. Related: bid math, financial statements and the B&F exam overview.

Practice questions

Practice question 1

Direct job costs are estimated at $200,000. The contractor adds overhead at 15% of direct cost, then profit at 10% of (cost + overhead). What is the bid price?

  1. A$250,000
  2. B$253,000
  3. C$230,000
  4. D$255,000
Show answer

Answer: B. Overhead: $200,000 x 1.15 = $230,000. Profit: $230,000 x 1.10 = $253,000. Adding 15% + 10% = 25% to cost ($250,000) ignores that profit is figured on cost plus overhead.

Source: Standard estimating arithmetic (verified in Python)

Practice question 2

A contractor wants a 20% gross profit MARGIN (profit as a percentage of selling price) on a job that costs $80,000. What selling price and what MARKUP on cost does that require?

  1. A$100,000 selling price; 25% markup
  2. B$96,000 selling price; 20% markup
  3. C$100,000 selling price; 20% markup
  4. D$96,000 selling price; 25% markup
Show answer

Answer: A. Price = cost / (1 - margin) = $80,000 / 0.80 = $100,000. Markup = profit / cost = $20,000 / $80,000 = 25%. Marking cost up 20% ($96,000) yields only a 16.7% margin.

Source: Standard markup vs. margin principle (verified in Python)

Practice question 3

A 25% markup on cost is equivalent to what gross margin on selling price?

  1. A25%
  2. B20%
  3. C33.3%
  4. D15%
Show answer

Answer: B. Margin = markup ÷ (1 + markup) = 0.25 ÷ 1.25 = 20%. Markup and margin are not equal; 33.3% is the markup needed for a 25% margin.

Source: Standard accounting principles

Practice question 4

Annual fixed overhead is $300,000. Each job's contribution margin ratio (revenue minus variable costs, as % of revenue) is 20%. What annual revenue is needed to break even?

  1. A$360,000
  2. B$1,500,000
  3. C$6,000,000
  4. D$240,000
Show answer

Answer: B. Break-even revenue = fixed costs ÷ contribution margin ratio = 300,000 ÷ 0.20 = $1,500,000. $360,000 merely adds 20% to fixed costs.

Source: Standard accounting principles

Practice question 5

A contractor installs units selling for $1,200 each with variable cost of $900 each. Fixed costs are $45,000 per year. How many units must it install to break even?

  1. A150 units
  2. B50 units
  3. C38 units
  4. D500 units
Show answer

Answer: A. Contribution per unit = 1,200 − 900 = $300; break-even = 45,000 ÷ 300 = 150 units. 50 units divides by the $900 variable cost; 38 divides by the price.

Source: Standard accounting principles

Practice question 6

A contractor allocates overhead on direct labor cost. Budgeted annual overhead is $240,000 and budgeted direct labor is $800,000. A job incurs $45,000 of direct labor. How much overhead should be applied to the job?

  1. A$10,385
  2. B$20,000
  3. C$13,500
  4. D$10,800
Show answer

Answer: C. Overhead rate = $240,000 / $800,000 = 30% of direct labor. Applied overhead = $45,000 x 30% = $13,500.

Source: Standard construction accounting principle (calculation verified in Python)

These are from our bank of 466 original questions. Get the full Florida Business & Finance prep.